Description:

1. Project Hawk Berm and Loading Dock Area Modifications

The works were undertaken in a busy operating area of the plant,. The involved the installation of new gabion walls, modifications to the existing Berm, and alterations to the existing trafficked roads and associated utility works. 

2. New Potable Water Tank CSA Works

Civils works including piling, excavation and tanks foundations, in a tight corner of the Pottery Road facility adjacent to neighbouring residential properties.

Key Facts / Information:

Client Amgen
MEP Consultant         Biopharma Engineering 
Civil & Structural Engineers Jacobs Engineering