Skip Navigation LinksPerdix Unit

Skip to Details
Data Hall Construction
Data Hall ConstructionData Hall Construction

Description:

Construction of a temporary Perdix Unit incorporating 5MVA power supply, back-up generator and 2 air handling units.The project included civils and structural works.

Technical Details 

  • 5 MVA Power Supply 
  • 1 x 2 MVA Back‐up Generators
  • 2 Air Handling Units
  • Redundancy Level N + 1
  • Tier 4 Classification

Key Facts / Information:

Client Confidential    
Civil / Structural Engineers CSEA
Services Engineer Callaghan Engineering
QS Kenneth Quinn and Associates
Location Dublin
Duration 2 months
Value €3,000,000